Massey Draw
As of April 28, 2018, Massey Draw is open to the public. While the day use facility is reopened, minimal construction activities will continue in the area through May 4, 2018. In order to protect the newly placed seeding and revegetation, some of the area has been fenced-off. Please be respectful of all fenced-off areas to allow for successful regrowth of vegetation.
Balloon Launch/Deer Creek Day Use Area
Due to poor weather conditions impacting paving and reseeding efforts, the reopening of the Balloon Launch, and nearby Deer Creek Day Use Area, has been delayed to May 15, 2018.
West Entrance – New Alignment
The new alignment at the Park’s West Entrance has been paved and traffic has been rediverted. Please keep in mind that the Perimeter Road remains CLOSED from south of the newly-aligned West Entrance to Kingfisher Day Use Area.
Kingfisher, Gravel Ponds, Marina, and other park amenities on the east side of the park are only accessible via the Park’s South Entrance off of Titan Road.
Plum Creek Day Use Area
Plum Creek Day Use Area is scheduled to be reopened to the public, for the 2018 summer season, the week of May 14th, 2018. Access to some of the shoreline to the east, especially access to the Plum Creek Nature Area, will be restricted. Work within the Plum Creek Nature Area is ongoing through 2018 and remains closed to the public.
Please continue to visit https://chatfieldreallocation.org/construction/ for the latest information on construction activities and closures.